Overview :
Learn key facts about Tajikistan’s Rogun Hydropower Project, including its 335-metre dam, Vakhsh River, 3,600 MW capacity, financing, and regional importance.
Rogun Hydropower Project
The Rogun Hydropower Project is being built on the Vakhsh River in Tajikistan . Its dam is planned to reach 335 metres . If completed as planned, it would become the world’s tallest dam.
Rogun Dam
Rogun is a rockfill dam with a clay core . A rockfill dam uses compacted rocks to form the main structure. The clay core helps reduce water seepage.
By August 2026, the dam had reached about 190 metres . Its elevation had reached around 1,155 metres above sea level .
Power Generation
Rogun will have six generating units . Each unit will have a capacity of 600 MW . Two units are already working.
The planned installed capacity is 3,600 MW . Some project documents mention a designed generation capacity of 3,780 MW .
Location and River System
Rogun lies upstream of the Nurek Hydropower Plant . It is about 110 km from Dushanbe , the capital of Tajikistan.
The Vakhsh River is a major tributary of the Amu Darya river system. So, the project has importance for Central Asia’s water and energy network.
Construction Work
Workers use underground tunnels to divert water during construction. They also strengthen the dam foundation.
By August 2026, workers had placed about 49 million cubic metres of material . They had also completed more than 500,000 metres of drilling for foundation work and the grout curtain.
Electricity and Regional Role
The completed project is expected to produce about 14,400 GWh of electricity every year . Tajikistan plans to use this power for domestic needs and winter shortages.
The country also plans to export electricity to Kazakhstan and Uzbekistan . Rogun can therefore support regional energy cooperation.
Financing
In June 2026, the World Bank approved an additional $300 million grant for the second phase. This would take its total planned financing to $650 million , according to the source.
Tajikistan also planned at least 10 billion somoni for Rogun financing in 2026. The total project cost is estimated at about $5.8 billion by 2035 .
Project Background
Construction began in 1976 during the Soviet period . Tajikistan later revived the project after the Soviet Union collapsed.
The third hydroelectric unit is scheduled for commissioning in the third quarter of 2027 , according to the source.
Why It Matters
Rogun is important for Tajikistan’s electricity supply and Central Asia’s energy network. It also shows how hydropower can support renewable electricity generation.
For India, the topic connects with hydropower, river systems, renewable energy, regional connectivity, and water management . These themes also matter for sustainable development and agricultural water security.
Exam-Focused Points :
- Project: Rogun Hydropower Project
- Country: Tajikistan
- River: Vakhsh River
- Planned dam height: 335 metres
- Planned capacity: 3,600 MW
- Generating units: 6 × 600 MW
- River basin: Vakhsh–Amu Darya system
FAQs :
Q1. Where is the Rogun Dam located?
It is located on the Vakhsh River in Tajikistan.
Q2. How high will the Rogun Dam be?
It is planned to reach 335 metres.
Q3. How many generating units will Rogun have?
It will have six units.
Q4. What is the planned installed capacity?
The planned capacity is 3,600 MW.
Q5. Which river system does the Vakhsh River join?
The Vakhsh River is part of the Amu Darya river system.